UBS DATA CENTRE

Hayes, Middlesex

Main Mechanical Contractor
Spie Matthew Hall
Main Contractor
Navarro Construction
Duration
6 weeks
Mechanical Project Value
£100,000
Project Manager
Spie Matthew Hall
Client
UBS
Project Status
Complete

The site was a live critical data centre operating 24 hours a day and 365 days a year. Our works were to provide new CHW distribution including both primary and secondary pipework to two new data halls within the centre. Due to the critical nature of the client’s operations the programme was fast-paced and required a high level of upfront planning and coordination. The project was successful and delivered well ahead of programme.