2 PARK STREET – CHILLER REPLACEMENT

Mayfair, London

Main Contractor
Leonari Ltd
Duration
6 Week
Mechanical Project Value
£220,000
Project Manager
ICFM Ltd/ Colliers International
Client
UK Property Span Ltd
Project Status
Complete

This works involved the replacement of two existing air-cooled chillers with a total cooling load of 416kW at roof level of the 2 Park Street office building, Mayfair, London.

The early stage procurement and selection of the chiller including booking of road closures for the crane lifts ensured that we could achieve the programme dates targeted by our client.

 Our scope of works also included the replacement of the BMS, CHW pumps, air dirt separators, dosing pot, pressurisation unit and associated pipework and valves on the CHW system at roof level. Modifications were also carried out to the existing trace heating systems with new insulation to the modified and new pipework.